In June 2024, Wildy Enterprises completed a complete generator replacement and controls installation project for the Rivers Inlet First Nations Band in a remote location on British Columbia’s coast.
The project involved removing two aging generators and installing a new 400kW prime power generator equipped with updated controllers and modernized switchgear integration.
Wildy’s role extended beyond installation. As a subcontracted generator installer, Wildy managed packaging, logistics, installation, commissioning, and the production of detailed documentation and drawings for the client.